April 17, 2014

The construction of Vostochny spaceport in Amur region is under way. The specialists work day and night to fill the gap in the schedule, – Vice Prime Minister Dmitry Rogozin stated.

“The construction works are under way, we work twenty four hours a day to come up with the schedule we were behind because of different reasons”, – Rogozin said.

At the present time about 6,1 thousand people work at spaceport construction, in summer the quantity of specialists will be increased by 3,5 thousands. Moreover we plan to involve students as well.

“We expect the last builder to leave the spaceport territory by July 2015 so that we could accomplish the 1st Soyuz-2 launch late 2015 as was planned”, – Rogozin concluded. The first manned launch is planned for 2018.

The first launching pad of Vostochny spaceport will be handed for assembling by May 15. Space device’s and booster’s main bodies will be also handed for assembling by that date.


More from this category:
Запуск ракеты-носителя «Протон-М» на космодроме Байконур
November 12, 2013

At 23.46 UTC on November 11 (03.46 Moscow time, November 12) Proton-M booster with Briz-M upper stage and Raduga-M military satellite was launched by Aerospace…

full story
June 9, 2015

ISS orbit was successfully adjusted on June 8, 2015 to avoid space debris. Progress M-26M cargo vehicle thrusters were ignited at 22.58, Moscow time, and…

full story
March 29, 2016

Aerospace indstry specialists completed general assembling of Soyuz-2.1a booster that is to launch new Russian cargo vehicle Progress MS-02 on March 31, – Roscosmos spokesman…

full story
August 20, 2014

On August 18, Roscosmos cosmonauts Alexander Skvortsov and Oleg Artemyev performed a spacewalk.  The cosmonauts started working at 18.02, Moscow time, and successfully completed the…

full story
June 10, 2015

Next Progress cargo vehicle will be launched with the help of Soyuz-U booster instead Soyuz-2.1a that failed to launch Progress M-27M on April 28. This…

full story
November 30, 2015

Today GCTC officially saw off ISS-46/47 prime (Yuri Malenchenko,  Roscosmos, Timothy Kopra, NASA, and Timothy Peake, ESA) and back-up (Anatoly Ivanishin, Roscosmos, Takuya Onishi, JAXA,…

full story
December 12, 2013

The docking of American Cygnus cargo vehicle with the ISS may be put off because of ISS thermal control system pump failure, – NASA representative…

full story
June 23, 2016

Proton boosters will be in use at least up to 2025. After that the quantity of launches will be reduced due to the gradual equipment…

full story